Wednesday, 17 June 2026

Vandana Garg, RP of Raguleela Builders Pvt. Ltd. Vs Mysore Petro Chemicals Ltd. - We consider that ideally, the appellant, as a resolution professional, even as he rejected the claim made by the respondent, still could have investigated and accepted the claim based on the original investment made by the respondent for the purchase of the commercial unit in lieu of the claim the respondent had made.

  NCLAT (2026.05.27)  in Vandana Garg, RP of Raguleela Builders Pvt. Ltd. Vs Mysore Petro Chemicals Ltd. [(2026) ibclaw.in 732 NCLAT, Company Appeal (AT) (Ins) No. 361 of 2024] held that;-

  •  “Section 14 of the IBC prescribes a moratorium on the initiation of CIRP proceedings and its effects. One of the purposes of the moratorium is to keep the assets of the corporate debtor together during the insolvency resolution process and to facilitate orderly completion of the processes envisaged under the statute.”

  • The judgement in ABG Shipyard case is set to the facts of that case, but what is significant is that Sec.14 does not permit or enable creation of any new liability against the corporate debtor from the date of commencement of CIRP, except those which are enabled by the Code to be treated as CIRP costs.

  •  If the case of the respondent is tested on the plane of this legislative philosophy on which Sec.14 of the Code is set, it would render ineffective the Order of the RERAA passed during the moratorium, creating a new liability on the CD. Necessarily, no claim based on the Order of the RERAA can be maintained.

  • We consider that ideally, the appellant, as a resolution professional, even as he rejected the claim made by the respondent, still could have investigated and accepted the claim based on the original investment made by the respondent for the purchase of the commercial unit in lieu of the claim the respondent had made.

Excerpts of the order;

This appeal is preferred by the Resolution Professional of the corporate debtor, in which he challenges the Order of the Adjudicating Authority dated 18.12.2023 allowing an application in I.A. 2725 of 2022 filed by the respondent herein for considering its claim of ₹ 5,20,22,000/- based on the Order of the Maharashtra Real Estate Regulatory Appellate Authority (for brevity would be referred to as RERAA). The RERAA has directed the CD to pay the respondent herein ₹5,20,22,000/-.


The Facts

# 2. The material facts are:

a) On 02.07.2015, the respondent had entered into an agreement for the purchase of a commercial unit with the CD. As per the agreement the unit was to be handed over to the respondent on 30.09.2015. The respondent has fully paid the consideration payable for the office unit to be purchased. The CD, however, did not deliver the unit as agreed upon.

b) The respondent, therefore, preferred a complaint with the RERA and vide its order dated 08.10.2020, the RERA dismissed the said complaint of the respondent. Challenging the said Order, on 17.12.2020, the respondent preferred an appeal to RERAA. Notice was ordered. According to the respondent, a notice was sent to the promoter of the project, the corporate debtor to be, through speed post, was served on it on 19.12.2020.

c) While the appeal preferred by the respondent was pending before the RERAA, CIRP commenced against the promoter of the project, vide the Order of the Adjudicatory Authority dated 04.10.2021. With that moratorium under Sec.14 of the Code came into force, IRP replaced the Board of the Corporate Debtor.

d) The IRP issued public notice inviting claims. The last date for preferring the claim was 05.11.2021. And the last date for filing belated claims in terms of Regulation 12 of the IBBI (CIRP) Regulations was 19.01.2022.

e) Be that as it may, on 30.06.2022, the RERAA allowed the appeal preferred by the respondent and directed the corporate debtor to pay a sum of. ₹5,28,22,000/- with interest at the rate of State Bank of India’s highest Marginal Cost Lending Rate plus 2% on the amount paid by the Respondent Company. On the following day, i.e., on 01.07.2022, the respondent e-mailed the appellant and informed them about the compensation ordered by the RERAA, and requested the appellant, the RP of the CD, to guide it to prefer the claim, and followed it with a reminder on 12.07.2022. Eventually, on 19.07.2022, the respondent preferred its claim in Form B.

f) The respondent, however, did not receive any information on the claim it had preferred, hence it moved the Adjudicating Authority with I.A.2725 of 2022 seeking a direction that its claim be considered. On 29.09.2022, the Adjudicating Authority passed an interim order and directed the appellant to consider the respondent’s claim.

g) Subsequent thereto, on 20.10.2022, the appellant rejected the claim of the appellant on two scores: (i) that the Order of the RERAA awarding compensation to the respondent was passed during the moratorium; and (b) that the claim was belated. (Regulation 13(1B) of the CIRP Regulation, enabling filing of claims till 7 days prior to the CoC voting on the resolution plan, came into effect only on 18.09.2023).


# 3. On 18.12.2023, the Adjudicating Authority has passed the final order in I.A.2725 of 2022 admitting the Claim of the respondent. It held: (i) that the respondent’s claim was not belated; and (ii) that the CD was bound by the judgement of the RERAA.


Arguments

# 4.1 The learned counsel for the appellant submitted:

a) The foundation of the claim of the respondent is an ex parte Order of the RERAA, dated 30.06.2022. However, this Order was passed after the moratorium was clamped under Sec.14 pursuant to the CD’s admission to CIRP vide the order of the Adjudicating Authority dated 04.10.2021. Law is settled vide the ratio in P. Mohanraj & Ors. v. Shah Brothers Ispat Pvt. Ltd. [(2021) ibclaw.in 24 SC] : [(2021) 6 SCC 258] and Real Estate Regulatory Authority Vs M/s D.B. Corp Ltd. [(2023) ibclaw.in 758 NCLAT] [CA (AT) (Ins) No. 1172- 1173 of 2022, dated 08.12.2023] where it has been held that any proceedings held during the period of moratorium is void and are incapable of creating enforceable rights.

b) If the Order passed initially by RERA is considered, it discloses that the respondent’s complaint has been the delay on the part of the CD in handing over possession of the office premises purchased. However, this complaint was dismissed by the RERA on 08.10.2020, on the ground that the delay in delivery was due to the delay in obtaining the Occupancy Certificate from the authorities. And, the agreement between the respondent and the CD provided for such a contingency, which binds the respondent herein, which the RERA had taken note of.

c) The next aspect is that on the admission of the CD to CIRP, the appellant duly issued a public notice through paper publication dated 21.10.2021 and invited claims from the creditors to be submitted by 05.11.2021. It was submitted that publication in newspapers in terms of Regulation 6 constituted a deemed notice to all creditors, including the respondent, terms of the dictum in M/s RPS Infrastructure Ltd. Vs Mukul Kumar & another [(2023) ibclaw.in 102 SC] : [(2023) 10 SCC 718]. But the appellant has filed its claim only on 19.07.2022 with a delay of about 198 days. By that time, the Information Memorandum had already been finalized and circulated to Prospective Resolution Applicants, and therefore entertaining such belated claims would derail the CIRP process.

d) Another aspect that flows directly from the effect of the public notice is that when the respondent has notice about the commencement of the CIRP and the moratorium on continuing with its appeal. However, the respondent not only suppressed the commencement of the CIRP but also continued serving notices on the erstwhile management of the CD instead of its Resolution Professional. Its effect is that the RP has been kept in the dark about the proceedings before the RERAA. This aspect has to be appreciated in the context of the fact that the erstwhile management of the CD has been least helpful in sharing the information and, the appellant was constrained to initiate a proceeding against them under Sec.19 IBC.

e) The appellant had acted with utmost diligence, hence no adverse inference can be drawn against him. Reliance was placed on M/s RPS Infrastructure (supra).


4.2 Concluding the arguments, the learned counsel submitted that the Adjudicating Authority, however, has erred in relying on the judgement in Power Grid Corporation of India Ltd. Vs Jyoti Structures Ltd. [(2017) ibclaw.in 12 HC] : [2017 SCC OnLine Del 12189 : (2018) 246 DLT 485] and disregarding the later judgment of the Hon’ble Supreme Court in P. Mohanraj case [(2021) 6 SCC 258]. In the process, the Adjudicating Authority has also overlooked the overriding effect of Sec.238 of the Code.


# 5. Per contra, the learned counsel for the respondent contended:

a) The respondent had instituted its appeal to the RERAA as early as December 2020, much prior to the commencement of CIRP against the Corporate Debtor on 04.10.2021. The notice of the appeal was duly served on the Corporate Debtor through multiple notices, e-mails, and reminders regarding the hearing dates were also issued. Despite such service, neither the corporate debtor nor the RP chose to appear before RERAA, therefore the CD is bound by the judgment dated 30.06.2022 passed therein.

b) On the aspect that the Order of the RERAA, as it was passed during the subsistence of moratorium, in ABG Shipyard Liquidator Vs Central Board of Indirect Taxes & Customs [(2022) ibclaw.in 103 SC]: [(2023) 1 SCC 472], the Hon’ble Supreme Court has held that any adjudicatory proceedings may continue during moratorium and that only recovery is prohibited. Therefore, the order passed by the RERAA is valid and binding upon the Corporate Debtor as well as the RP.

c) So far as the allegation that the claim was preferred belatedly is concerned, the respondent could not have filed its claim prior to the adjudication of the proceedings before the RERAA, since the claim crystallised only upon the order dated 30.06.2022 directing payment of interest to the Respondent. Immediately thereafter, the Respondent informed the RP by email dated 01.07.2022 and sought guidance for filing its claim under the Code, and subsequently filed its claim in Form B on 19.07.2022 at the earliest possible opportunity. Hence, there was no delay attributable to the Respondent in lodging its claim.

d) At any rate, Sections 18, 25 and 29 of the IBC read with Regulation 36 of the CIRP Regulations create a statutory obligation on the IRP or the RP, as the case may be, to collect and collate all claims against the corporate debtor and to keep itself apprised of all pending litigation involving the CD. The Information Memorandum was also required to disclose all material litigation and disputes concerning the CD. Consequently, the RP cannot evade its statutory responsibility by contending that it lacked information regarding the proceedings before RERAA. Indeed, these provisions taken along with Regulation 14(2) statutorily obligate an IRP or a RP to revise admitted claims whenever additional information comes to light. It was submitted that the CIRP framework itself contemplates revision and up-dation of claims during the CIRP process, therefore rejection of the Respondent’s claim solely on the ground of delay is contrary to the scheme of the Code and Regulations.

e) At any rate, the timeline fixed for collation of claims is only directory as held in State Tax Officer Vs Rainbow Papers Limited [(2022) ibclaw.in 107 SC]: [(2023) 9 SCC 545] and hence, claims cannot be rejected merely on account of delay where the resolution plan has not attained finality. Indeed, where a claim is discernible from the records of the corporate debtor, and the resolution plan has not been approved, then a delay in submitting the claim cannot be held against the creditor of the corporate debtor.

f) So far as the application of Sec.238 of the Code goes, in Pioneer Urban Land and Infrastructure Ltd. Vs Union of India [(2019) ibclaw.in 13 SC] : [AIR 2019 SC 4055], it is held that the remedies under the RERAA and the IBC are concurrent and complementary in nature, and hence there exists no inconsistency warranting the invocation of Section 238 of the Code.

g) The appellant did not challenge the interim Order of the Adjudicating Authority, dated 29.09.2022, and had considered the Claim. Having considered the claim, which, according to the appellant, was preferred belatedly, the argument that the claim was belatedly filed loses much of its sheen. Indeed, the appellant is estopped from contending about the delay in preferring the claim.


Discussion & Decision

# 6.1 The core issue, which is critical to the outcome of this appeal, is about the maintainability of the Claim, which undisputably is founded on an Order of the RERAA passed during the operation of the moratorium. It instantly relegates the alleged failure of the respondent to notify the appellant about the pendency of its appeal before the RERAA to insignificance. After all, even if the RP had been notified about the appeal, given the fact that Sec.14(1)(a) of the code prohibits ‘the continuation of pending suits or proceedings against the corporate debtor including execution of the judgement, decree or order in any court of law, tribunal or beneficial interest therein”, the Order of the RERAA will necessarily come under the scanner of the Code. The idea behind moratorium, as contemplated under Sec.14, is to freeze the assets and liabilities of the CD during CIRP for optimizing the value of the assets of CD to enable a successful resolution process and pay off the liabilities of the CD out of the proceeds of the resolution process in the manner contemplated under Sec.53 of the Code. In ABG shipyard case [(2023) 1 SCC 472], the Hon’ble Supreme Court has observed (paragraph 38), “Section 14 of the IBC prescribes a moratorium on the initiation of CIRP proceedings and its effects. One of the purposes of the moratorium is to keep the assets of the corporate debtor together during the insolvency resolution process and to facilitate orderly completion of the processes envisaged under the statute.


6.2 Turning to the effect of the moratorium in P. Mohanraj case [(2021) 6 SCC 258], the Supreme Court has held that the moratorium operates absolutely on all pending suits or proceedings (though the Court drew a distinction between suit and proceedings) and they will come to a standstill. This view was later followed in Anjali Rathi & Others Vs Today Homes & Infrastructure Pvt., Ltd., & others [(2021) ibclaw.in 152 SC] : [(2021 SCC OnLine SC 729]. However, the respondent has contended that the Order of the RERAA is not invalidated in terms of the dictum in ABG Shipyard case [(2023)1 SCC 472]. In that case, the Supreme Court has held that while the Customs Officials may assess or determine the quantum of customs duty payable by the CD during the period of moratorium, it may not still be permissible for it to take steps to recover the same during moratorium, and that issuance of any demand notices during the subsistence of moratorium is hit by Sec.14 of the Code. The judgement in ABG Shipyard case is set to the facts of that case, but what is significant is that Sec.14 does not permit or enable creation of any new liability against the corporate debtor from the date of commencement of CIRP, except those which are enabled by the Code to be treated as CIRP costs.


6.3 If the case of the respondent is tested on the plane of this legislative philosophy on which Sec.14 of the Code is set, it would render ineffective the Order of the RERAA passed during the moratorium, creating a new liability on the CD. Necessarily, no claim based on the Order of the RERAA can be maintained.


# 7. If the claim is not maintainable, then it does not matter whether it is filed within time or belated. Therefore, we do not propose to deal with that issue.


# 8. Having stated thus, there is another angle to the issue of the respondent’s entitlement to a claim. Admittedly, the respondent invested in a built-up commercial space and claims to have paid the entire sale consideration of ₹12,93,60,000/-. If the RP has replaced the Board of the CD, and if he is aware of the projects that the CD had undertaken, then it will not be difficult for the resolution professional to ascertain and identify the allottees and the amounts they had paid. It may be that when, on 21.10.2021, the RP issued a public notice in terms of Sec.15, Regulation 6A of the IBBI(CIRP) Regulations was not there, but when the RP is required to prepare a list of assets and liabilities of the CD in discharge of his duty under Sec.18(1), will it not be appropriate for him to include investments innocently and bona fide made even though they may not have preferred a claim? On going through the reply of the RP to the application of the respondent herein before the Adjudicating authority, he has not disputed the claim of allotment made to the respondent. Indeed, the fact that RERA and RERAA have considered the complaint of the respondent establishes that an allotment indeed has been made by the corporate debtor. In our opinion, RP should have realized that IBC is neither designed as a statute for the divestiture of individual rights, nor is it fashioned as an expropriatory statute. On the other hand, IBC is keen to recognize every right to claim a debt, which it defines as debt, even though it holds no promise to any creditor that the debt due to him will be paid. Here we are at the point of recognizing the right of the respondent at least to the money it has invested for the purchase of a commercial unit from the Corporate Debtor. In that sense, a claim is but a notice to the resolution professional that the corporate debtor is liable to repay a debt to a certain creditor. But if that debt could be ascertained without a formal claim, would it not be appropriate and fair for the RP to ascertain the same and seek the one to whom the debt is due from the corporate debtor? We consider that ideally, the appellant, as a resolution professional, even as he rejected the claim made by the respondent, still could have investigated and accepted the claim based on the original investment made by the respondent for the purchase of the commercial unit in lieu of the claim the respondent had made.


# 9. In conclusion, we dispose of the appeal with a direction to the resolution professional to verify if the respondent had made any payment of consideration to the corporate debtor as claimed by it and to include its claim.

-------------------------------------------------------------


Monday, 8 June 2026

Kotak Mahindra Bank Limited vs Ashok Oswal & Ors - Locus to challenge admission of claim - The Adjudicating Authority may proceed to decide I.A No. 368 of 2020 on merits after hearing the Learned Counsel for the parties at the earliest..

NCLAT (2022.04.04)  in Kotak Mahindra Bank Limited vs Ashok Oswal & Ors. [Company Appeal (AT) (Insolvency) No. 575 of 2021] held that;-

  • We may also notice that in the Application I.A. No. 368 of 2020, the Respondent No.1 has challenged the acceptance of the claim of the Appellant by the Liquidator. On the other hand, the Respondent No.1 has refuted the locus of the Appellant to challenge the decision of the Liquidator accepting the claim.

  • The Adjudicating Authority may proceed to decide I.A No. 368 of 2020 on merits after hearing the Learned Counsel for the parties at the earliest..

Blogger’s Comments; Here the following provision of the IBC is worth noting;

  • Section 70. Punishment for misconduct in course of corporate insolvency resolution  rocess. -

  • (1) On or after the insolvency commencement date, where an officer of the corporate debtor

  • XXXX

  • (d) fails to inform their resolution professional the information in his knowledge that a debt has been falsely proved by any person during the corporate insolvency  resolution process; or . . .


Excerpts of the order;

# 1. This Appeal has been filed by ‘Kotak Mahindra Bank Limited’, a Financial Creditor of Corporate Debtor- ‘Oswal Spinning & Weaving Mills Limited’ seeking direction to the Adjudicating Authority to adjudicate and dispose of the Applications I.A No. 368 of 2020 and I.A No. 555 of 2020. We need to notice certain facts and events prior to filing of the Appeal and subsequent to the filing of the Appeal which are necessary to be noticed for deciding this Appeal.


# 2. The Corporate Insolvency Resolution Process (CIRP) was initiated by order dated 30.10.2018 passed by the Adjudicating Authority (National Company Law Tribunal), Chandigarh Bench, Chandigarh, in CP (IB) No. 136/Chd/Pb/2017. No Resolution Plan could be obtained. An Application under Section 33(1)(a) of the Insolvency and Bankruptcy Code, 2016 (“Code” for short) was filed by the Resolution Professional praying for an order of liquidation. The Adjudicating Authority vide its order dated 13.12.2019 allowed the Application of the Resolution Professional and directed for liquidation of the Corporate Debtor. The liquidation process started after the order dated 13.12.2019. In the liquidation, the Liquidator invited claims from the Financial Creditors. The Appellant i.e. ‘Kotak Mahindra Bank Ltd.’ as well as Respondent Nos.2 to 5, other Financial Creditors filed their claim. Liquidator partly admitted the claim of the Appellant. During the Liquidation Proceedings, I.A No. 368 of 2020 was filed by the Respondent No.1- Suspended Director of the Corporate Debtor. On the Application I.A No. 368 of 2020, the Adjudicating Authority passed an ex-parte interim order on 09.09.2020 directing the Liquidator to maintain status quo with regard to distribution of funds to the Respondent Nos.2 to 5 to the application. After the aforesaid ex-parte interim order, the Appellant- ‘Kotak Mahindra Bank Ltd.’ filed an I.A No. 555 of 2020 under Section 60(5) of the Code r/w Rule 49 of the NCLT Rules, 2016 for recall of the order dated 09.09.2020. On 21.10.2020, the Adjudicating Authority issued notice in I.A No. 555 of 2020. I.A No. 368 of 2020 and I.A No. 555 of 2020 were listed before the Adjudicating Authority on several occasions but could not be decided. The Appellant filed Company Appeal (AT) (Ins.) No.21 of 2021 seeking direction to the Adjudicating Authority to dispose of the I.A No. 368 of 2020 and I.A No. 555 of 2020 in a time bound manner which Appeal was disposed of by this Appellate Tribunal by order dated 19.01.2021 requesting the Adjudicating Authority, Chandigarh Bench to expedite the process and dispose of the same within three months. The order dated 19.01.2021 of this Tribunal was placed before the Adjudicating Authority which also took note of the order and fixed a date for hearing in February, 2021. Both the Applications I.A No. 368 of 2020 and I.A No. 555 of 2020, in spite of more than eight dates fixed before the Adjudicating Authority, remained pending. The Appellant thereafter filed present Company Appeal (AT) (Ins.) No. 575 of 2021 again seeking for direction to the Adjudicating Authority to decide the Applications I.A No. 368 of 2020 and I.A No. 555 of 2020. This Appeal was initially heard by this Appellate Tribunal and by judgment and order dated 10.08.2021 the Appeal was finally disposed of.


# 3. The Appellant aggrieved by judgment of this Tribunal dated 10.08.2021, filed an Appeal before the Hon’ble Supreme Court in Civil Appeal No. 6944 of 2021. The Hon’ble Supreme Court after hearing the Appellant took the view that this Appellate Tribunal ought not to have finally disposed of the Appeal and Appellate Tribunal could have kept the Appeal pending, while awaiting compliance from the Adjudicating Authority. The Hon’ble Supreme Court further vide its order dated 26.11.2021 restored the Company Appeal (AT) (Ins.) No. 575 of 2021 for further consideration. The Hon’ble Supreme Court observed that the Chandigarh Bench of the Tribunal is unable to hear the matter on the next date i.e. 12.01.2022 and decide the same within 15 days thereof, the Appellant Tribunal would be free to pass such other order/s as may be required, including that of modifying the ex parte interim order of the Tribunal or of withdrawing the matter from the file of Chandigarh Bench of the Tribunal and to decide itself or to assign the same to any other Bench of the Tribunal.


# 4. After judgment of the Hon’ble Supreme Court in Civil Appeal No. 6944 of 2021 dated 26.11.2021, this Appeal was restored and was taken by this Tribunal on 13.12.2021 where the Appeal was adjourned to 28.01.2022 awaiting the order of the Tribunal which was to be passed within 15 days from 12.01.2022. When the matter was again taken up by this Tribunal on 28.01.2022, Learned Counsel for the Respondent No.1 submitted that it has filed an Application to recall the order dated 26.11.2021 as per liberty given by the Hon’ble Supreme Court. Hence, the order of the Hon’ble Supreme Court be awaited. The Adjudicating Authority having fixed the matter on 24.02.2022, this Tribunal observed that the Adjudicating Authority may consider the Application for vacation of the ex parte interim order, if no order is obtained from the Hon’ble Supreme Court by the Respondent No.1.


# 5. On 14.02.2022, the Hon’ble Supreme Court dismissed the Miscellaneous Application No. 252 of 2022 filed by the Respondent No.1 in Civil Appeal No. 6944 of 2021. By order dated 14.02.2022, the Hon’ble Supreme Court again requested this Appellate Tribunal to take up the Appeal for consideration and pass such orders as may deem fit and necessary, keeping in view of the observations and expectations in the order passed by the Hon’ble Supreme Court on 26.11.2021.


# 6. After the order of the Hon’ble Supreme Court on 14.02.2022, this Appeal was again taken on 28.02.2022, when the Counsel for the parties informed that the Adjudicating Authority has started hearing the matter and next date fixed for hearing is 08.03.2022. We adjourned the Appeal to 25.03.2022 awaiting the orders of the Adjudicating Authority.


# 7. On 25.03.2022, when this Appeal was taken, we were informed that the Applications were not still decided. We observed that we need to decide the Applications I.A No. 368 of 2020 and I.A No. 555 of 2020 as per the orders of the Hon’ble Supreme Court since the Adjudicating Authority has been unable to decide the matter. On 25.03.2022, Learned Counsel for the Respondent No.1 sought liberty to file certain documents which was granted and matter was posted for hearing on 28.03.2022. When matter was taken up on 28.03.2022, this Tribunal was informed that the Adjudicating Authority is still hearing the matter and the next date fixed is 07.04.2022. We proceeded to hear the Applications I.A No. 368 of 2020 and I.A No. 555 of 2020 on 28.03.2022.


# 8. We have heard Shri Manish Jain, Learned Counsel for the Appellant and Shri Ankur Mittal, Learned Counsel for Respondents.


# 9. Few facts and sequences of the events regarding two Applications i.e. I.A No. 368 of 2020 and I.A No. 555 of 2020 need to be noticed, before we proceed to consider the submissions of the Learned Counsel for the Appellant. As noted in the liquidation proceedings, Respondent No.1- Suspended Director of the Corporate Debtor filed an Application I.A No. 368 of 2020 where following prayers have been made:-

  • “RELIEF

  • 1. Quash the acceptance of the claim of Respondent Nos. 2 to 5 by the Respondent No.1; and direct Respondent No.1 to await the final adjudication of the claims pending before the Hon’ble Debt Recovery Tribunal or the Hon’ble Punjab and Haryana High Court, or any other authority/Court/Tribunal as the case may be, before any claim for payment of financial dues on behalf of Respondent Nos. 2 to 5 can be accepted and monies accordingly disbursed.

  • 2. Direct the Respondent No.1, to effectively contest the claims made by the corporate debtor before various Courts/Tribunals, in order to discharge his legal obligations under the IB Code 2016.

  • 3. Pass such other orders as may be deemed fit and proper by this Hon’ble Tribunal in the facts and circumstances of the case.

  • INTERIM RELIEF

  • 1. Pending consideration of the reliefs as aforesaid, restrain the Respondent No.1 from disbursing any funds to Respondent Nos. 2 to 5;

  • 2. Direct the Respondent No.1, to effectively contest the claims made by the Corporate Debtor before various Hon’ble Courts/Tribunals, in order to discharge his legal obligations under the IB Code 2016;

  • 3. Pass such other orders as may be deemed fit and proper by this Hon’ble Tribunal in the facts and circumstances of the present case.”


# 10. Application I.A No. 368 of 2020 was taken by the Adjudicating Authority on 09.09.2020 and following order was passed:-

  • “IA No.368/2020

  • This IA has been filed by the Suspended Managing Director of M/s. Oswal Spinning and Weaving Mills Ltd. which is undergoing liquidation proceedings against the Liquidator and certain other claimants under Section 60(5) of the Code read with Section 42 of the Insolvency and Bankruptcy Code, 2016 aggrieved with the decision of the Liquidator in admitting the claims of respondent Nos. 2 to 5. Heard the learned Senior Counsel for the applicant. Issue notice to the respondents and the applicant counsel shall collect the same from the Registry and send along with copy of the application and the entire paper book to the respondents by Speed Post immediately as well as at the e-mail address available and file affidavit of service along with postal receipt, tracking report and copy of e-mail within 10 days.

  • 2. Opportunity is given to the respondents to file reply/objections, if any, within two weeks from the receipt of the notices and rejoinder thereto, if any, may be filed within one week thereafter with copy in advance to the counsel opposite. List the matter on 21.10.2020.

  • 3. In the meanwhile, the respondent No.1 Liquidator shall maintain status quo with regard to the distribution of funds to respondent Nos. 2 to 5.”


# 11. After the order dated 09.09.2020 was passed restraining Respondent Nos. 2 to 5 i.e. Financial Creditors which included the Appellant before us, an Application I.A No. 555 of 2020 was filed by the Appellant for recall of the ex parte order dated 09.09.2020 on 14.10.2020. Both the Applications I.A No. 368 of 2020 and I.A No. 555 of 2020 were taken up on 21.10.2020 and following order was passed by the Adjudicating Authority:-

  • “IA No.368/2020

  • 10. Heard Ms. Salina Chalana, the learned counsel for the applicant. Though notices were directed to be served on 09.09.2020 but the applicant failed to serve the notices to the respondents. At the request of the applicant’s counsel issue fresh notices to the respondents in the IA for 10.11.2020 and applicant shall collect the notices from the Registry and send the same by speed post immediately to the respondents at their registered addresses attaching therewith copy of the application and the entire paper book and the copy of this order.

  • 11. The applicant shall file affidavit of service supported by acknowledgment of receipt of notices within one week from today failing which they are liable to pay cost of Rs.25,000/- in favour of “The Prime Minister’s National Relief Fund”.

  • 12. Reply be filed within one week after receipt of notice with a copy in advance to the counsel opposite.

  • 13. The interim order granted on 09.09.2020 is extended till the next date of hearing of the IA and if the applicant failed to serve the notice on the respondents within one week from today, as observed above, the interim order shall stands vacated.

  • 14. List on 10.11.2020.

  • IA No. 555/2020

  • 17. This IA has been filed by Kotak Mahindra Bank Limited seeking to set-aside the ex-parte order dated 09.09.2020 passed in IA No. 368/2020. Heard Mr. Manish Jain, the learned counsel for the applicant.

  • 18. Issue notice of this application to the respondents for 10.11.2020 and the applicant shall collect the notices from the Registry and send the same by speed post immediately to the respondents at their registered addresses attaching therewith copy of the application and the entire paper book and the copy of this order.

  • 19. The applicant shall file affidavit of service supported by acknowledgment of receipt of notices within one week.

  • 20. Reply be filed within one week after receipt of notice with a copy in advance to the counsel opposite.

  • 21. List this IA alongwith IA No. 368/2020 on 10.11.2020.”


# 12. There has been several dates fixed before the Adjudicating Authority after 21.10.2020 but the Applications could not be disposed by the Adjudicating Authority. Hence, Company Appeal (AT) (Ins.) No. 21 of 2021 was filed by the Appellant asking this Appellate Tribunal to issue direction to the Adjudicating Authority for adjudication of the Applications I.A No. 368 of 2020 and I.A No. 555 of 2020. This Appellate Tribunal on 19.01.2021 passed following orders:-

  • “19.01.2021: The impugned order is not an order adjudicating upon the rights of the parties. It merely says that due to paucity of time, the matter stands adjourned to 18th January, 2021, which date has already elapsed. Mr. Manish Jain, Advocate representing the Appellant submits that even yesterday i.e. on 18th January, 2021, the matter could not be taken up and it has again been adjourned. Corporate Insolvency Resolution Process arising out of an admission of an application under Section 7 of the Insolvency and Bankruptcy Code, 2016 is stated to have culminated in passing of an order of liquidation a year before and liquidator is stated to have sold some of the assets.

  • We share the concern of learned counsel for the Appellant who being a Financial Creditor, is concerned about further depletion in the value of the assets affecting its claim. We accordingly dispose off this appeal by requesting the Adjudicating Authority (National Company Law Tribunal), Chandigarh Bench, Chandigarh to expedite the process and dispose off the same within three months.”


# 13. This Tribunal in the aforesaid order requested the Adjudicating Authority to expedite the process and dispose of the matter which obviously meant Applications I.A No. 368 of 2020 and I.A No. 555 of 2020 on which I.As orders were under challenge.


# 14. When even after order dated 19.01.2021, the Adjudicating Authority could not dispose of both the Applications I.A No. 368 of 2020 and I.A No. 555 of 2020, again Company Appeal (AT) (Ins.) No. 575 of 2021 was filed which was initially disposed of by this Tribunal on 10.08.2021 where in para 5, this Tribunal observed:-

  • “5. Considering the above and keeping in view our order dated 19th January, 2021 which could not be complied as three months are already over, we do express anguish with regard to the delay. We do realise the difficulties of the litigants as well as difficulties being faced by the Tribunal. In the circumstances, we dispose of the present Appeal with only a request to the Adjudicating Authority to take out time and decide the present IAs at the earliest.”


# 15. Against the order dated 10.08.2021, the Appeal was filed by the Appellant before the Hon’ble Supreme Court. The Hon’ble Supreme Court noticing the proceedings taken on I.A No. 368 of 2020 and I.A No. 555 of 2020 and the orders of this Tribunal passed on 19.01.2021 and 10.08.2021, by order dated 26.11.2021 disposed of the Appeal and made following observations:-

  • “The only aspect relevant in the present case is that the IAs pending before the Adjudicating Authority need to be decided without further loss of time. For that matter, the Adjudicating Authority is definitely expected to keep in view the requirement of expeditious proceeding under the Insolvency and Bankruptcy Code, 2016 as also the directions issued by the Appellate Tribunal, even if expressed in soft terms.

  • We are informed that the said order dated 10.08.2021 was passed by the Appellate Tribunal without notice to the opposite party. We are further informed that even after the said order dated 10.08.2021, the Adjudicating Authority adjourned the matter on 11.10.2021 and again on 02.11.2021; and the matter is now fixed by the Adjudicating Authority for consideration on 12.01.2022.

  • We are clearly of the view that in the given set of circumstances, the Appellate Tribunal, while reiterating its request to the Adjudicating Authority to decide the pending IAs at the earliest, ought not to have disposed of the appeal. Rather, the Appellate Tribunal could have kept the appeal pending, while awaiting compliance from the Adjudicating Authority and, if necessary compliance was not yet forthcoming, to withdraw the matter from the National Company Law Tribunal, Chandigarh Bench, Chandigarh and either to dispose of itself or transfer it to some other Bench of the Tribunal for necessary steps.

  • In the aforesaid view of the matter, without notice to the other side, we set aside the last paragraph (No.6) of the order impugned, whereby the appeal has been disposed of by the Appellate Tribunal.

  • Instead, the said appeal bearing No. 575 of 2021 is restored for further consideration of the Appellate Tribunal. If Chandigarh Bench of the Tribunal is still unable to final hear the matter on the next date, i.e., 12.01.2022 and to decide the same within 15 days thereof, the Appellate Tribunal would be free to pass such other order/s as may be required, including that of modifying the ex parte interim order of the Tribunal or of withdrawing the matter from the file of Chandigarh Bench of the Tribunal and to decide itself or to assign the same to any other Bench of the Tribunal.

  • We are constrained to pass this order when it appears that Adjudicating Authority has not been able to adhere to the timelines as per the requirements of law as also the orders passed by the Appellate Tribunal. As at present, we say no more.

  • However, we deem it appropriate to observe that this order is passed without notice to the other side particularly after noticing that the appeal was disposed of by the Appellate Tribunal without notice to the opposite party. Yet, in the interest of justice, we leave it open that in case any opposite party seeks modification of this order or proposes to make any other submission, it shall be permissible for it to move appropriate application for consideration. It goes without saying that we have not made any comments on merits of the case either way. The present appeal stands disposed of accordingly.”


# 16. The Hon’ble Supreme Court in the above order clearly observed that if the Chandigarh Bench of the Tribunal is unable to finally hear the matter on 12.01.2022 and to decide the same within 15 days thereof, the Appellate Tribunal would be free to pass such other order/s as may be required. After the judgment of the Hon’ble Supreme Court dated 26.11.2021, when the matter was again taken by this Tribunal, the Respondent No.1 has informed about filing of the Application for recall of the order dated 26.11.2021 which Application stood dismissed on 14.02.2022. It will be relevant to notice the following observations made by the Hon’ble Supreme Court:-

  • “It is rather disturbing to note that despite specific orders of the Appellate Tribunal as also of this Court, the Adjudicating Authority has not been able to decide the pending applications and now, the submissions before us on behalf of the respondent No.1 (applicant) are to the effect that there ought not to be “tearing hurry” in deciding those applications. Such a proposition on the part of the applicant cannot be countenanced, particularly looking to the previous orders passed in the matter, as noticed hereinabove.

  • It is also noticed from the record that though we had restored the said appeal before the Appellate Tribunal so that appropriate and necessary orders could be passed, the Appellate Tribunal has chosen not to pass any other order in the matter, for the reason that the present application was said to be pending in this Court.

  • Taking the totality of facts and circumstances into account, the application so moved by respondent No.1 of the appeal is specifically rejected. We would request the Appellate Tribunal to immediately take up the appeal for consideration and to pass such orders as may be deemed fit and necessary, keeping in view the observations and expectations in the order passed by this Court on 26.11.2021.


# 17. In view of the orders passed by the Hon’ble Supreme Court, we indicated to the Learned Counsel for the parties that I.A No. 368 of 2020 and I.A No. 555 of 2020 need to be heard by this Tribunal and we proceeded to hear the parties.


# 18. Learned Counsel for the Appellant submits that the ex parte order dated 09.09.2020 passed in I.A No. 368 of 2020 was obtained by the Respondent No.1 without serving him copy of the Application. It is submitted that under National Company Law Tribunal Rules, 2016 by virtue of Rule 23 sub-rule (5), it was incumbent on the Respondent No.1 to serve a copy of the Application by which he was seeking to stay the disbursement to the Financial Creditors. It is further submitted that the ground taken in the Application that since counter claim of the Corporate Debtor is pending before the DRT, Chandigarh, no disbursement could be made to the Financial Creditors in the liquidation proceedings till the counter claim is decided was wholly irrelevant. It is submitted that the liquidation proceedings in the IBC cannot be held to be dependent on any proceeding pending in the DRT. It is submitted that the counter claim filed by the Corporate Debtor against one of the Banks i.e. UCO Bank has already been dismissed which has also been noticed by this Appellate Tribunal in Company Appeal (AT) (Ins.) No. 763 of 2018- 

  • “Mr. Ashok Oswal vs. UCO Bank & Anr.” which was filed by the Respondent No.1 himself. It is submitted that the Respondent No.1- Suspended Director has no locus to challenge the admission of the claim of the Appellant by the Liquidator. Under Section 42 of the Code, it is only the Creditor who have given right to challenge the order of the Liquidator. There was no locus of the Respondent No.1 to file Application I.A No. 368 of 2020.


# 19. Shri Ankur Mittal, Learned Counsel appearing for the Respondent No.1 refuting the submissions of the Learned Counsel for the Appellant submits that Respondent No.1 has every right to challenge the decision of the Liquidator erroneously accepting the claim of the Appellant. It is submitted that there are no dues which are owed by the Corporate Debtor to the Appellant. Liquidator has wrongly accepted the partial claim of the Appellant with regard to which Respondent No.1 being aggrieved filed the Application. It is submitted that in the Insolvency Resolution Process itself, the Respondent No.1 has filed an Application challenging the admission of the claim by Resolution Professional which Application could not be decided on merits. It is further submitted that the counter claim filed by the Corporate Debtor before the DRT is necessary to be decided which will prove that no debt is due to the Appellant. The counter claim has been filed by the Corporate Debtor against the Appellant also. It is further submitted that the Liquidator has not taken any step to prosecute the counter claim before the DRT. It is submitted that it is the duty of the Liquidator to prosecute the claim of the Corporate Debtor before the DRT. The counter claim was filed by the Corporate Debtor even before initiation of CIRP. It is submitted that the Counsel is not aware that the Application I.A No. 368 of 2020 was filed after serving copy on the Appellant or not.


# 20. Shri Abhishek Anand, Learned Counsel for the Liquidator submits that the claims were invited by the Liquidator in accordance with the Liquidation Process, 2016 and above process cannot be subject to any other proceeding. The Liquidator cannot keep the proceeding pending awaiting decision of the DRT. The Application filed by the Respondent No.1- Suspended Director was not maintainable as the Respondent No.1 is asking something which he cannot do directly. If the lender received more amount, they are liable to refund the same as per Regulation 43 and there was no occasion for the Adjudicating Authority to pass any interim order on 09.09.2020.


# 21. We have considered the submissions of the parties and perused the record.


# 22. We have noticed the prayer made in the Application I.A No. 368 of 2020. There are two main grounds taken in the Application for seeking reliefs as prayed in the Application. In the Application, the acceptance of the claim of Respondent Nos.2 to 5 was sought to be quashed and further to direct the Liquidator to await the final adjudication of the claim pending before the DRT or the Hon’ble Punjab & Haryana High Court. The first submission of the counsel for the Appellant is that I.A No. 368 of 2020 was filed by the Respondent No.1 without serving an advance copy of the Application to the Appellant. Rule 25 deals with “presentation of petition or appeal”. Sub-rule (5) of Rule 25 provides as follows:-

  • “25. Presentation of petition or appeal .- …………..(5) In the pending matters, all applications shall be presented after serving copies thereof in advance on the opposite side or his authorised representative.”


# 23. The Application I.A No. 368 of 2020 was filed in a pending matter where relief was sought against the Respondent Nos. 2 to 5- Financial Creditors to the Application which included the Appellant. Respondent No.1 wanted interim order against the Financial Creditors but the Application was not served. The contention of the Learned Counsel for the Respondent No.1 is not that the Application I.A No. 368 of 2020 was filed after service of the copy rather it has submitted he does not have any instructions as on date. The fact that copy of the Application I.A No. 368 of 2020 was not served is fully proved by subsequent order dated 21.10.2020 where the Adjudicating Authority has noted that Learned Counsel for the Applicant (Counsel for Respondent No.1) has not served the notice to the Respondents. We have already extracted the order dated 21.10.2020 in foregoing discussion.


# 24. We, thus, are fully satisfied that Application I.A No. 368 of 2020 was filed without serving copy on Appellant who was to be affected by the interim order. Furthermore, it is relevant to notice Application I.A No. 368 of 2020 was filed on 28.07.2020 and it came for consideration on 09.09.2020 hence more than one month’s time was available to Respondent No.1 to serve copy on the Appellant. The order dated 09.09.2020 was ex parte which is clear from the order itself. In the present case, interim order affecting the claim of the Financial Creditors for distribution of funds by Liquidator has been estopped.


# 25. The Appellant has immediately filed an Application I.A. No. 555 of 2020 before the Adjudicating Authority for recall of the ex parte order dated 09.09.2020. The main plea of the Respondent No.1 in I.A No. 368 of 2020 is that if the DRT decides the counter claim of the Corporate Debtor no distribution be permitted in the liquidation process. The pendency of the

counter claim of the Corporate Debtor before the DRT cannot be ground to stay the distribution to the Financial Creditors as per the claim admitted by the Liquidator. Proceedings under the IBC are time bound proceedings which has an overriding effect by virtue of Section 238. In the facts of the present case, we are of the view that I.A No. 555 of 2020 filed by the Corporate Debtor for recall of the ex parte order ought to have been allowed by the Adjudicating Authority. The Adjudicating Authority has not decided the said I.A for more than period of one year and five months. In spite of two orders passed by this Tribunal and judgment of the Hon’ble Supreme Court dated 26.11.2021 and 14.02.2022, we see no justification in continuing the interim order dated 09.09.2020 staying the distribution to the Financial Creditor in the liquidation process. By order of the Adjudicating Authority, the claim of the Financial Creditor to receive the disbursement has adversely affected and they are not able to receive the disbursement as per their claim.


# 26. Learned Counsel for the Liquidator has referred to Regulation 43 of the Insolvency And Bankruptcy Board Of India (Liquidation Process) Regulations, 2016 which provides following:-

  • “43. Return of money. A stakeholder shall forthwith return any monies received by him in distribution, which he was not entitled to at the time of distribution, or subsequently became not entitled to.”


# 27. Regulation 43 amply take care of any excess amount to any stakeholders. We may also notice that in the Application I.A. No. 368 of 2020, the Respondent No.1 has challenged the acceptance of the claim of the Appellant by the Liquidator. On the other hand, the Respondent No.1 has refuted the locus of the Appellant to challenge the decision of the Liquidator accepting the claim. It has been submitted before us that hearing in Application I.A. No. 368 of 2020 has already been commenced before the Adjudicating Authority in which next date is 07.04.2022. We, thus, are of the view that in this Appeal the only Application I.A No. 555 of 2020 needs to be finally decided by modifying interim order dated 09.09.2020 by deleting the following part of the order dated 09.09.2020:

  • In the meantime, the Respondent No.1 Liquidator shall maintain status quo with regard to the distribution of funds to respondent Nos.2 to 5”


# 28. Thus, the order dated 09.09.2020 is modified to the above extent and the interim order is recalled/ vacated. It shall be open for the Adjudicating Authority to proceed with the Application I.A No. 368 of 2020 and pass final order on the said Application. In view of the fact that hearing has already been commenced by the Adjudicating Authority on merits of the Application I.A No. 368 of 2020, we make it clear that our observations in this judgment are confined only to extent of only allowing the Application I.A No. 555 of 2020 and modifying the interim order dated 09.09.2020 and we may not be understood to express any final opinion on the contention which are still to be decided in I.A No. 368 of 2020. In view of the above, we dispose of the Appeal with following directions:-

  • (i) I.A No. 555 of 2020 is allowed. Interim order dated 09.09.2020 directing the Liquidator to maintain status quo with regard to distribution of funds to Respondent Nos. 2 to 5 are recalled/ vacated. Application I.A No. 555 of 2020 is disposed of.

  • (ii) The Adjudicating Authority may proceed to decide I.A No. 368 of 2020 on merits after hearing the Learned Counsel for the parties at the earliest..

-------------------------------------------------------------