Tuesday, 24 December 2024

Harpal Singh Chawla Vs. Vivek Khanna and Ors.- It is true that when a unit holder is handed over possession and a Conveyance Deed has also been executed, no claim survives of such unit holders.

 NCLAT (2024.12.17) in Harpal Singh Chawla Vs. Vivek Khanna and Ors.  [(2024) ibclaw.in 831 NCLAT, IA No.7853 of 2024 in Company Appeal (AT) (Insolvency) No. 2002 of 2024] held that;

  • It is true that when a unit holder is handed over possession and a Conveyance Deed has also been executed, no claim survives of such unit holders. 

  • Whether a claim filed by a Financial Creditor in a class, deserves admission, is a question, which need to be first looked into by the RP as per the statutory regulations governing the collation and verification of the claim. 

  • At this stage, whether the claim filed by a particular Financial Creditor in a class before the RP is admissible or not is a question, which need to be looked into by the IRP and thereafter by the Adjudicating Authority and any aggrieved person has ample remedy by filing application under Section 60 sub-section (5), if any claim has wrongly been admitted, which ought not to have been admitted by the RP.


Excerpts of the Order;

IA No.7853 of 2024

IA No.7853 of 2024 has been filed by the Applicant/ Appellant praying for following reliefs:

  • “a) modify the Order dated 28.10.2024 passed by this Hon’ble Adjudicating Authority in the Company Appeal (AT)(lns) No. 2002 of 2024 to the effect that the CIR Process of the Corporate Debtor may be confined to the single Project namely ‘Spaze Arrow’ for which the Section 7 Petition was filed before the Ld. Adjudicating Authority and the Committee of Creditors be constituted for the said Project only; and

  • b) such other and further orders be passed as facts and circumstances of the case may require.”


# 2. Company Appeal (AT) (Ins.) No.2002 of 2024 has been filed by the Suspended Director of the Corporate Debtor – Spaze Towers Pvt. Ltd. challenging order dated 21.10.2024 passed by National Company Law Tribunal, New Delhi Bench, Court-IV admitting Section 7 Application filed by Respondents (Respondent Nos.1 to 26 – Financial Creditor in a class). The Respondents – Financial Creditors in a class being allottee of a Project namely ‘Spaze Arrow’ located at Sector 78, Gurugram filed Section 7 Application claiming a default on the Corporate Debtor (“CD”) seeking initiation of Corporate Insolvency Resolution Process (“CIRP”) against the CD. The Adjudicating Authority after hearing the parties by order dated 21.10.2024 admitted Section 7 Application. Aggrieved by the said order, this Appeal was filed by Suspended Director of the CD. In the Appeal, following order was passed on 28.10.2024:

  • 28.10.2024: Issue Notice.

  • 2. Let Reply be filed within three weeks.

  • 3. Intervenors are permitted to file the Intervention Application before the next date fixed.

  • List this Appeal on 16th December, 2024.

  • In the meantime, insolvency in pursuance of the Impugned Order shall go on which will be abide by the result of the Appeal.

  • Let the CoC be constituted.”


# 3. The Appellant aggrieved by the order dated 28.102.024 passed by this Tribunal in the present Appeal filed Civil Appeal No.12189 of 2024 – Harpal Singh Chawla vs. Vivek Khanna & Ors., which Civil Appeal has been disposed of by order of the Hon’ble Supreme Court dated 08.11.2024. Order passed by Hon’ble Supreme Court on 08.11.2024 is as follows:

  • “The grievance raised by the appellant, Harpal Singh Chawla (a suspended Director of Spaze Towers Pvt. Ltd.), is that there are twelve completed projects and the Corporate Insolvency Resolution Process should not be initiated in respect of those projects.

  • We make no comments in this regard, as the matter is sub-judice before the National Company Law Appellate Tribunal. We leave it open to the appellant, Harpal Singh Chawla, to approach the National Company Law Appellate Tribunal by way of an appropriate application pointing out the relevant facts and consequences for consideration.

  • We clarify that we have not made any observations on the merits of the case and the contentions raised by the parties.

  • The appeal and pending application(s), if any, shall stand disposed of.”


# 4. After the above order of the Hon’ble Supreme Court, present IA No.7853 of 2024 has been filed by the Appellant on 08.11.2024 itself, praying for reliefs as noted above. In IA No.7853 of 2024, learned Counsel for the Respondents took time to file reply to the Application, which was allowed on 21.11.2024. Reply has been filed by the Respondent, to which a rejoinder affidavit has also been filed by the Appellant in pursuance of the liberty granted on 28.11.2024. Several Intervention Applications have been filed by the allottees in the present Appeal, which shall be noticed hereinafter.


# 5. We have heard Shri Mukul Rohatgi, learned Senior Counsel appearing for the Appellant/ Applicant; Shri Abhijeet Sinha, learned Senior Counsel appearing for Respondent Nos.1 to 26 (Financial Creditors in a class); Shri Rishabh Jain, learned Counsel for Resolution Professional (“RP”); Shri Abhimanyu Bhandari, learned Senior Counsel appearing on behalf of Intervenor in IA Nos.7995 and 8215 of 2024; Shri Gaurav Mitra, learned Counsel appearing for Applicant in IA No.8241 of 2024; Shri Krishnendu Datta, learned Senior Counsel appearing in IA No.8253 of 2024 and other learned Counsel appearing for the Intervenors.


# 6. Shri Mukul Rohatgi, learned Senior Counsel appearing for the Applicant/Appellant submits that CIRP against the CD be confined to Project namely – ‘Spaze Arrow’ only. It is submitted that Respondent Nos.1 to 26, creditors in class are of the Project Spaze Arrow and to initiate CIRP against the CD, filed Application under Section 7, which relate to only one Project namely – Spaze Arrow. Hence, the CIRP, be confined to only one Project, i.e. Spaze Arrow. It is submitted that CD is a reputable developer in the National Capital Region and has completed 12 Projects in and around Gurugram region. Learned Counsel for the Applicant has referred to Annexure-2 to the Application, which contains the details of 12 Projects with regard to which Occupancy Certificates have been received. With regard to 05 Projects out of 12 Projects, Completion Certificates have also been received, details of which are mentioned in Annexure-2. It is submitted that some Projects were completed ten years ago. It is submitted that the Projects, which have already been completed, need not be taken in the CIRP. The Projects being complete, most of the allottees have already been handed over possession, who are living in their units. Initiation of CIRP with regard to 12 completed Projects, shall be prejudicial to the interest of the allottees and put the Projects in jeopardy, which have already been completed. It is submitted that CIRIP of the CD at best could have been restricted to the single Project, i.e. Spaze Arrow. The learned Counsel for the Appellant/ Applicant submits that Appellant has filed Civil Appeal against the order dated 28.10.2024 passed by this Tribunal and the Hon’ble Supreme Court had granted liberty to the Applicant to move appropriate Application before this Tribunal. Hence, this Tribunal may modify its order dated 28.10.2024 and confine the CIRP to only single Project, i.e. Spaze Arrow. It is submitted that the Appellant is not shying away from its obligation to compete the development of the said Project, however, due to the non-cooperation of the Co-Promoter, Mr. Ishan Singh by initiating various proceedings against the CD, various order has been obtained including an interim order against the CD. Hence, the CD could not complete the construction of the Project. It is submitted that projected yield returns from the Projects Spaze Arrow is about Rs.250 crores and there being 325 unsold units, Project can very well be completed. The CoPromoter obtained a status quo order on 02.12.2019, vide which the construction of the troubled Project was halted and could not be completed by the CD. It is submitted that in 12 completed Projects, approximately 6700 units have been successfully constructed and out of total number of units, 6653 have been sold to third party allottees and in most of the cases, possession of the same have been either given or have been offered to the respective allottees. The troubled Project Spaze Arrow is also feasible and viable.


# 7. Shri Abhijeet Sinha, learned Senior Counsel appearing for Respondent Nos.1 to 26 (the Financial Creditors in a class), who initiated proceedings, submits that the prayer made in the Application, cannot be granted. It is submitted that the CD abandoned the Project Spaze Arrow and according to own case of the Appellant/ Applicant, due to dispute raised by the land owners and due to interim orders passed against the CD, the Project could not be completed. It is submitted that in pursuance of the order dated 21.10.2024 passed by Adjudicating Authority, the IRP has already issued publication, in pursuance to which Committee of Creditors (“CoC”) has already been constituted, which consist of 100% creditors in a class. It is submitted that IRP has received the claims from the allottees of nearly all Projects. The IRP has admitted claims worth Rs.72 crores from 228 allottees from across all Projects of the CD. The IRP has sent letter dated 13.11.2024 for constitution of the CoC and an Agenda was also issued for the first Meeting of the CoC to be held on 19.11.2024. It is submitted that the CD earlier also had been admitted to CIRP vide order dated 28.10.2021 passed by NCLT, New Delhi in CP(IB) 889 of 2020, which Application was filed by the allottees of Project ‘Spaze Corporate Park’ under Section 7, in which the claims of Rs.610 crores were collated by the IRP from the Financial Creditors. The CD ultimately settled with the original petitioners and the CIRP was set aside by the Hon’ble Supreme Court vide its order dated 18.11.2021 in Civil Appeal No.6798 of 2021. It is submitted that on account of failure of the CD to abide by the undertaking, the Hon’ble Supreme Court has already issued notice on 17.09.2024 to the CD in Contempt Petition No.683 of 2024. The CoC having already been constituted, comprising of 228 allottees across all Projects, confining CIRP to only Spaze Arrow Project would amount to denial of rights to Financial Creditors, who have already filed their claims, which have been admitted by the IRP. It is submitted it is for the CoC to take a decision as to whether Resolution Plan be invited for each real estate Project or a group of Projects of the CD. It is submitted that an Arbitral Award has been passed on 14.09.2022 in arbitration proceedings initiated by CD, according to which the CD is unable to carry on any construction. The CD’s objection against Arbitral Award has also been dismissed. It is further submitted that Department of Town and Country Planning, Haryana vide order dated 01.07.2024 has suspended the Project’s license.


# 8. Shri Abhimanyu Bhandari, learned Senior Counsel appearing for Ishan Singh, the land owner, referring to his IA No.7995 of 2024 (for Impleadment) and IA No.8215 of 2024 (to initiate criminal proceedings against the CD) contends that CD has no right to carry on any construction on the Project land. Shri Ishan Singh, who is the land owner, who has initially entered into Collaboration Agreement with the CD in the year 2010, had already cancelled the Collaboration Agreement and there is an Arbitral Award dated 14.09.2022, under which the CD has no right to carry out any work in pursuance of Collaboration Agreement. The CD has unsuccessfully challenged the Arbitral Award dated 14.09.2022 by filing Section 34 Application, under Arbitration and Conciliation Act, 1996, which has also been dismissed. It is submitted that CD has no right to carry out any construction on the Project land, which is undisputedly owned by Ishan Singh. It is submitted that the Appellant has concealed various relevant facts in the Appeal and the IA. It is submitted that CD was also earlier subjected to CIRP by an order passed by Adjudicating Authority on Applications filed by allottees of Project ‘Spaze Corporate Park’, which ultimately was settled by the CD before the Hon’ble Supreme Court. The Appellant has made various false averments and there are huge dues of DTCP on the CD, which have not yet been paid.


# 9. Large number of Intervention Applications have been filed in the Appeal by several unit holders of Project ‘Spaze Corporate Park’ like IA No.8024 of 2024 and IA No.8021 of 2024 – Vandana Raheja and 33 others, who had earlier filed Section 7 Application against the CD being CP(IB) No.889 of 2020, which was admitted on 28.10.2021. Another IA No.8217 of 2024 filed by Lalita Mehta, who claimed that possession and Conveyance Deed have been granted with regard to Spaze Corporate Park. Other IAs, like IA No.8253, 8273, 8030 and 8031 of 2024 have also been filed by different Applicants. With regard to other Projects also, large number of IAs have been filed. IA No.8241 of 2024 has been filed with regard to Project ‘Spaze Tristaar’. IAs, which have been filed for intervention, can be divided in two sets. One set of IAs are with regard to claims filed before the IRP in pursuance of publication issued by the IRP and they are Financial Creditors, belong to different Projects, including Spaze Arrow and Spaze Corporate Park. Other set of IAs are filed by those Applicants, who claim that they are in possession of the units. Some of them have also claimed that Conveyance Deed has been executed in their favour. Several Intervenors have also filed claims before the IRP, only claiming for execution of Conveyance Deed in their favour.


# 10. We have considered the submissions of learned Counsel for the parties and have perused the records.


# 11. The submissions of learned Counsel for the Appellant is founded on the ground that CD has completed 12 Projects, apart from Spaze Arrow, with regard to which Section 7 Application was filed. Hence, CIRP be confined to only Spaze Arrow Project. In Annexure-2 to the Application, the Appellant has given the details of 12 Projects, dates of issuance of Occupancy Certificates and Completion Certificates. It is useful to extract Annexure-2 to the Application, which is as follows:

  • “1. Spaze Towers Private Limited starting its operation and executed 13 Projects, out of which 12 Projects have been delivered and the occupation certificates have been received. The only 1 Project which is left namely “Spaze Arrow” situated at Sector 78, Gurugram, Haryana under dispute with Land Owner Mr. Ishan Singh.

  • Complete details of all the 12 Projects completed by Spaze Towers Private Limited are attached for your kind perusal.


12. A perusal of above Annexure indicate that the CD has obtained Occupancy Certificate and out of 12 Projects, for 05 Projects the CD has obtained Completion Certificate. ‘Occupancy Certificate’ is dealt in Clause 4.10 of The Haryana Building Code, 2017, which is as follows:


“4.10. Occupation Certificate

(1) Every person who intends to occupy such a building or part thereof shall apply for the occupation certificate in Form BR-IV(A) or BR-IV(B), which shall be accompanied by certificates in relevant Form BR-V(1) or BR-V(2) duly signed by the Architect and/ or the Engineer and along with following documents:

(i) Detail of sanctionable violations from the approved building plans, if any in the building, jointly signed by the owner, Architect and Engineer.

(ii) Complete Completion drawings or as-built drawings along with completion certificate from Architect as per Form BR-VI.

(iii) Photographs of front, side, rear setbacks, front and rear elevation of the building shall be submitted along with photographs of essential areas like cut outs and shafts from the roof top. An un-editable compact disc/ DVD/ any other electronic media containing all photographs shall also be submitted.

(iv) Completion certificate from Bureau of Energy Efficiency (BEE) Certified Energy Auditor for installation of Rooftop Solar Photo Voltaic Power Plant in accordance to orders/ policies issued by the Renewable Energy Department from time to time.

(v) Completion Certificate from HAREDA or Bureau of Energy Efficiency (BEE) Certified Energy Auditor for constructing building in accordance to the provision of ECBC, wherever applicable.

(vi) No Objection Certificate (NOC) of fire safety of building from concerned Chief Fire Officer or an officer authorized for the purpose.

(2) No owner/ applicant shall occupy or allow any other person to occupy new building or part of a new building or any portion whatsoever, until such building or part thereof has been certified by the Competent Authority or by any officer authorized by him in this behalf as having been completed in accordance with the permission granted and an ‘Occupation Certificate’ has been issued in Form BRVII. However, Competent Authority may also seek composition charges of compoundable violations which are compoundable before issuance of Form BRVII. Further, the water, sewer and electricity connection be released only after issuance of said occupation certificate by the Competent Authority.

(3) The ‘Occupation Certificate’ shall be issued on the basis of parameters mentioned below:-

(i) Minimum 25% of total permissible ground coverage, excluding ancillary zone, shall be essential for issue of occupation certificate (except for industrial buildings) for the first time or as specified by the Government: Provided, in case of residential plotted, minimum 50% of the total permissible ground coverage shall be essential to be constructed to obtain occupation certificate, where one habitable room, a kitchen and a toilet forming a part of submitted building is completed.

(ii) The debris and rubbish consequent upon the construction has been cleared from the site and its surroundings.

(4) After receipt of application, the Competent Authority shall communicate in writing within 60 days, his decision for grant/ refusal of such permission for occupation of the building in Form BR-VII. The E-register shall be maintained as specified in Code-4.8 for maintaining record in respect of Occupation Certificate.

(5) If no communication is received from the Competent Authority within 60 days of submitting the application for “Occupation Certificate”, the owner is permitted to occupy building, considering deemed issuance of “Occupation certificate” and the application Form BR-VII shall act as “Occupation Certificate”. However, the competent authority may check the violations made by the owner and take suitable action.

(6) If the owner or Architect or Engineer or Consultant as mentioned in Code 4.11(1)(i), (iv), (v) and (vi) as the case may be, submits a wrong report while making application under this Code or if any additional construction or violation is reported to exist at site or has concealed any fact or mis-represented regarding completion of construction of building along with its eligibility for seeking occupation certificate or before the completion of such report, he shall be jointly and severally held responsible for such omission and complaint against the Architect for suspension of his registration and the owner shall be liable to pay for the penalty as may be decided by the competent authority after giving an opportunity of hearing. Further, if it is emerged that the information is concealed by Engineer/ Consultant/ Owner, necessary penal proceedings will be initiated along with debarring Engineer/ Consultant/ Architect from practicing in the State of Haryana.”


# 13. The ‘Completion Certificate’ is dealt in The Haryana Development and Regulation of Urban Areas Act, 1975. Rule 16 deals with ‘Completion Certificate/ Part Completion Certificate’, which is as follows:

  • 16. Completion certificate/Part Completion Certificate [Section 24].— 139[(1) After the colony has been laid out according to approved layout plans and development works have been executed according to the approved designs and specifications, the coloniser shall make an application to the Director in Form LC-VIII alongwith a demand draft on account of Infrastructure Augmentation Charges as per the rates prescribed in the Schedule-B of these rules if not paid earlier in accordance with the provision of Section 3(7) of the Act.]

  • (2) After such [scrutiny], as may be necessary, the Director may issue a [completion certificate/part completion certificate] in form LC-IX or refuse to issue such certificate stating the reasons for such refusal:

  • Provided that the colonizer shall be afforded an opportunity of being heard before such refusal.”


# 14. The above statutory provisions provide for issuance of Occupancy Certificate and Completion Certificate and the Appellant’s case is that for all 12 Projects, he has obtained Occupancy Certificate and for 05 Projects Completion Certificate. Clause 4.10 as noted above provide that every person who intends to occupy a building or part thereof shall apply for the Occupation Certificate, which shall be accompanied by relevant certificates. Occupation Certificate is, thus, a pre-condition for occupying a premises or building. The facts, which have been brought on record, indicate that in pursuance of CIRP commencement against the CD, the claims have been filed by the allottees of Spaze Arrow and other different Projects. The Respondent has brought on record the list of unsecured Financial Creditors of real-estate allottees as Annexure-B. The Appellant in his rejoinder affidavit has also brought the same list of creditors as on 13.11.2024 as Annexure-30. A perusal of the list of creditors indicate that real-estate allottees, who have filed the claim from Sl. No.1 to 38 are with regard to Project Spaze Arrow and Sl. No.39 to 98 are claims regarding Project Corporate Park. Sl. No.99 to 105, are claims with respect of Business Park and Sl. No.106 to 168 are claims from the Project Tristaar. Sl. No. 169 to 180 are from Project Privy AT 4 and Sl. No.181 to 194 are claims for Project Privy The Address. Sl. No.195 to 202 are claims for Platinum Tower Project and Sl. No.203 to 216 for Project Tech Park. Sl. No.217 to 220 are claims for Project Boulevard-I and Sl. No.221 to 227 are for Project Plazo. Sl. No.228 is a claim for Spaze Delhi. From the list of creditors, it is clear that the claims filed by the allottees were to an amount of Rs.1,819,796,643/-. Out of which, the IRP has admitted claim of Rs.727,507,352/- and claims of Rs.868,961,658 is under verification.


# 15. The Respondents, who had filed Application under Section 7, relate to Project Spaze Arrow, with regard to which claims have already been filed as noted above. The next Project for which several claims have been filed is the Project ‘Corporate Park’. We need to notice certain facts and pleadings pertaining to Corporate Park. As per Annexure-2 to the Application, the Occupancy Certificate for Corporate Park was obtained on 28.01.2020 and Completion Certificate was obtained on 25.06.2021. It is on the record that Company Petition No. IB 889/ND/2020 was filed by Vandana Raheja and 39 Ors. of “Project Corporate Park”, which was admitted by NCLT, New Delhi, Court No.IV by order dated 28.10.2021. Thus, the CIRP against the CD commenced on 28.10.2021, i.e., subsequent to Occupancy Certificate or Completion Certificate as was obtained by the CD for Project Corporate Park. Against the order dated 28.10.2021, an Appeal was filed before this Tribunal, in which no interim order was passed. Hence, Civil Appeal No.6798 of 2021 was filed before the Hon’ble Supreme Court, challenging order of this Tribunal, which Appeal was disposed of on account of settlement between the contesting parties. The order of the Hon’ble Supreme Court dated 18.11.2021 passed in Civil Appeal No.6798 of 2021 has been brought on record as Annexure-E to the reply filed by Respondent Nos.1 to 26.


# 16. With regard to Project Corporate Park, IA No.8024 of 2024 and IA No.8021 of 2024 was filed by Vandana Raheja and Ors., who had earlier initiated Section 7 Application against the CD in CP(IB) No.889 of 2020. The Applicant – Vandana Raheja in its IA seeks intervention and in IA No.8024 of 2024 detailed facts are mentioned. It is pleaded that Project Spaze Corporate Park developed by the CD is incomplete. Reference to Writ Petition (C) No.8523 of 2020 – Vandana Raheja & Ors. vs. Union of India & Ors. has also been made, where Delhi High Court has appointed Local Commissioner on 09.02.2021 to inspect the construction. The Local Commissioner has also submitted a Report on 22.02.2021, which has also been brought on the record along with IA No.8024 of 2024. It is relevant to notice that CIRP against the CD for Project Corporate Park had commenced on 28.10.2021, i.e. date subsequent to CD having obtained Occupancy Certificate and Completion Certificate. The said proceedings were ultimately set-aside on account of settlement before the Hon’ble Supreme Court on 18.11.2021. Large number of Claimants have filed claim arising from the Project Corporate Park, as noticed above.


# 17. When CIRP was commenced against the CD, all Financial Creditors are entitled to file claim as per the Insolvency and Bankruptcy Board of India (Insolvency Resolution for Corporate Persons) Regulations, 2016. The claim is defined in Section 3, sub-section (6) of the IBC, which is as follows:

  • “3(6) “claim” means –

  • (a) a right to payment, whether or not such right is reduced to judgment, fixed, disputed, undisputed, legal, equitable, secured, or unsecured;

  • (b) right to remedy for breach of contract under any law for the time being in force, if such breach gives rise to a right to payment, whether or not such right is reduced to judgment, fixed, matured, unmatured, disputed, undisputed, secured or unsecured;


# 18. The real-estate allottees are Financial Creditors as per provisions of the IBC and in event any real-estate allottee has a claim against the CD, he is fully entitled to file a claim on commencement of the CIRP against the CD.


# 19. It is true that when a unit holder is handed over possession and a Conveyance Deed has also been executed, no claim survives of such unit holders. Whether a claim filed by a Financial Creditor in a class, deserves admission, is a question, which need to be first looked into by the RP as per the statutory regulations governing the collation and verification of the claim. At this stage, whether the claim filed by a particular Financial Creditor in a class before the RP is admissible or not is a question, which need to be looked into by the IRP and thereafter by the Adjudicating Authority and any aggrieved person has ample remedy by filing application under Section 60 sub-section (5), if any claim has wrongly been admitted, which ought not to have been admitted by the RP.


# 20. As noted above, when the Claimants have filed claims for the Project Corporate Park, which we have noted above and who have pleaded that the Project is not complete despite Occupancy Certificate and Completion Certificate, by confining the CIRP to only one Project – Spaze Arrow, shall tantamount to excluding the claims filed before the RP from different Project. We, thus, after considering the facts and circumstances, which have been brought on the record by the parties, are of the view that at this stage, we are not persuaded to pass an order, confining the CIRP to only one Project, i.e. Spaze Arrow, as prayed in the Application filed by the Appellant/ Applicant. The prayer made in the IA No.7853 of 2024 cannot be allowed. IA No.7853 of 2024 is rejected.


----------------------------------------


Monday, 23 December 2024

Hotline Glass Limited Majdoor Sangh Vs. Mr. Jigar Pradipchandra Shah - RP’s contention that the claim pertains to year 2007 and is barred by limitation is not acceptable, as the limitation act provides limitations for filing an appropriate application before a Tribunal or Court and does not specify a period to file a claim before the resolution professional in case of initiation of CIRP.

 NCLT Indore (2024.11.20) in Hotline Glass Limited Majdoor Sangh Vs. Mr. Jigar Pradipchandra Shah  [IA/308/MP/2023 in IA/280/MP/2022 In TP/152/MP/2019, CP(IB)/99/2019] held that;

  • RP’s contention that the claim pertains to year 2007 and is barred by limitation is not acceptable, as the limitation act provides limitations for filing an appropriate application before a Tribunal or Court and does not specify a period to file a claim before the resolution professional in case of initiation of CIRP. 


Excerpts of the Order;

# 1. This present application has been filed on 10.10.2023, by Hotline Glass Limited Majdoor Sangh (Applicant) through Mr. Ashish Tiwari (Authorized representative), under section 60(5) of the Insolvency and Bankruptcy Code, 2016 r.w. Rule 11 of the NCLT Rules, 2016, against Mr. Jigar Pradipchandra Shah, Resolution Professional (RP) of the corporate debtor i.e., Hotline Glass Limited, seeking directions to set aside the order of the resolution professional rejecting the claim of the applicant and to direct the resolution professional to admit the claim of the applicant.


# 2. The averments made by the applicant in the present application and as argued by the learned PCS are summarized as under:

(i) The applicant is the association of labours who were working in Hotline Glass Limited. The corporate debtor was put into Corporate Insolvency Resolution Process (CIRP) by the Adjudicating Authority vide order dated 13.03.2020.

(ii) The corporate debtor has illegally closed its factory in the year 2007 and various workmen/employees have not been paid salary, hence, the employees have informed the Labour Commissioner, Indore whereby the Labour Commissioner had issued three Revenue Recovery Certificate (RRC) No. 52/18/three/7/14680-86 dated 22.06.2007, RRC No. 4/16/three/8/6576-82 dated 05.03.2008, and RRC No. 2/16/three/2023/4181-87 dated 03.02.2023 under the power vested in section 33 C (1) of Industrial Dispute Act, 1947 for Rs 26,05,548/-, Rs 54,42,943/- and Rs 30,33,819/- respectively against the corporate debtor. Said RRCs have been issued for recovery of unpaid salary from the period January 2007 to March 2007, April 2007 to December 2007 and January 2008 to March 2009.

(iii) The applicant has also filed a writ petition bearing No. 8244/2021 before the Hon’ble High Court of Madhya Pradesh, Gwalior being aggrieved by the inaction of the respondents (Collector and ors.) in the writ petition, on not receiving/paying the amount of Rs 54,42,943/- as directed by the Deputy Labour Commissioner, Indore vide its RRC dated 05.03.2008. Hon’ble High Court vide its order dated 08.04.2021 directed the Collector to implement RRC within three months from the date of receipt of the order.

(iv) The respondents therein in the said writ petition had failed to comply with the abovementioned order dated 08.04.2021, therefore the applicant filed a contempt petition bearing No. 2432/2021 before the Hon’ble High Court, which is pending.

(v) The applicant was not in knowledge of the CIRP initiated against the corporate debtor, hence, the applicant could not file the claim before the respondent within time.

(vi) The RP has not accepted the claim form by stating that he has not received any claim from the applicant during CIRP, prior to the last date of submission of claim as per public announcement and even prior to the submission of resolution plan before the Adjudicating Authority for approval.

(vii) The details of claim form submitted by the applicant before the RP is as under: . . . 

(viii) The applicant then approached this Adjudicating Authority to consider the claim form as the applicant with bona fide reason has failed to submit their claim on time. This Adjudicating Authority vide order dated 11.08.2023 has condoned the delay in filing the claim before the RP and directed the RP to examine the claim and take a decision as per the law.

(ix) The RP had raised a query at the time of verifying claim and the applicant has given a reply to the query raised by the RP. However, the RP without considering the reply given by the applicant has erroneously rejected the claim of the applicant by stating that the claim filed by the applicant is time barred. The claim of two applicants namely Manoj Kumar Awasthi and Rishikesh Sharma has neither been admitted nor rejected by the RP till date.

(x) The amount claimed by the applicant is not time barred, as Limitation Act, 1963 is not applicable to the proceedings of Industrial Dispute Act, 1947. The Hon’ble Apex Court in the matter of “Nityanand M Joshi Versus Life Insurance Corporation and Sai Prabhakar Versus Joint Director Sericulture” clearly held that the Limitation Act, 1963 is not applicable to the proceedings of Industrial Dispute Act, 1947. Therefore, there is no limitation for claiming amount arising from RRC. It is also submitted that the Hon’ble High Court vide its order dated 08.04.2021 directed the respondent No. 2/Collector to implement the RRC, so from such order it can be clearly ascertained that there is no time limit for execution of RRC. Therefore, the respondent herein has rejected the claim of the applicant on the basis of time barred claim, which is totally wrong and unlawful in the eyes of law.

(xi) The Hon’ble Apex Court in the matter of ‘Kotak Mahindra Bank versus A Balakrishnan’ has clearly held that a claim arising out of a recovery certificate would be a financial debt within the meaning of clause (8) of section 5 of the Code. Consequently, the holder of recovery certificate would be a financial creditor within the meaning of clause (7) of section 5 of the Code.

(xii) It is further submitted that by virtue of section 6 of the Revenue Recovery Act, 1890, the claim on the property of corporate debtor has been created by issuance of the RRC, therefore the applicant must be treated as secured creditor under section 3(30) of the Code, because the security interest has been created in favour of the applicant.

(xiii) Applicant in their claim form has claimed amount from three different RRCs, as well as their salary from year 2009 till the CIRP commencement date and payment of gratuity and earned leave. The applicant herein requests the Adjudicating Authority to allow the claim of the applicant arising from three different RRCs and outstanding payment of Gratuity. As the amount claimed by the applicant from year 2009 till CIRP commencement date is disputed, therefore, the applicant is not claiming such aforesaid amount in the present application.

(xiv) The details of the amount arising from three RRCs mentioned above read as under:

(xv) Gratuity is the right of the applicant, so the applicant is hereby claiming gratuity amount as well. The calculation of the gratuity amount according to section 4 of Payment of Gratuity Act, 1972 as follows: .  . . .

(xvi) It is submitted that appointment letter of Mr. Arun Nigam has been misplaced, therefore, it is kindly requested to consider his claim of gratuity in the interest of justice.


# 3. In this context, defence placed by the respondent in its affidavit in reply are summarized here as under:

(i) After due deliberation and examination of the claims, documents and records available, the respondent herein, vide E-mail dated 09.09.2023, had rejected the claims of the workmen after enumerating the following reasons:

  • “We have gone through all such documents,

  • 1. Your claim amount is from 2007.

  • 2. The operation of the factory was closed in 2007 because of obsolete technology and non-viability of the project.

  • 3. No case is going on with any of the courts.

  • 4. The CIRP was admitted by Hon. NCLT on 13.03.2020.

  • 5. In CIRP provision, no time limit is specified for admission of claim but however, the time barred is not considered. You have calculated claim from 01.01.2007 till 13.03.2020. There was no electricity connection, or security to the factory. The factory was completely closed. Further, there is no evidence of attendance sheet, communications, etc. if you are claiming that you were working in the factory. Hence, the claim amount from 2007 till 2020 is also wrongly calculated considering the salary for all these years.

  • 6. Further, section 53 of the Code specifies that workers claim till 24 months before the liquidation commencement date has to be considered.

  • Hence, considering the claim is as time-barred as it is for the year 2007, we reject your claim.”

(ii) Admittedly, a total claim of Rs 83,12,822/- is filed before the respondent. A bare perusal of the claim forms produced by the applicant in annexure A/7 (page no. 112 to 152) of the amended application would clearly reveal that no bifurcation of such claim is given by any of the workmen under their respective claim forms.

(iii) The applicant herein suo-moto reduced the claim of the workmen to the extent of RRCs issued by the Learned Labour Commissioner, Indore dated 22.06.2007, 05.03.2008 and 03.02.2023. Thus, now merely a total amount of Rs 12,07,750/- is claimed by the applicant. The said fact itself indicates that the workmen have duly agreed with the decision of the respondent that they are not entitled to claim an amount of Rs 83,12,822/- and hence, their claims are rejected on valid grounds by the respondent.

(iv) Not a single workman has worked in the said factory as it was completely closed after February 2007. Therefore, there exists no evidence such as attendance sheet, any communication etc. in support of the workmen, so as to establish that the workmen were actually working in the said factory of the corporate debtor.

(v) The RRC dated 22.06.2007 and 05.03.2008, based on which the workmen have filed their claims, are issued by the Learned Labour Commissioner in year 2007 and 2008. Subsequent to this, there is nothing to indicate that the workmen have perused their claims for such an elongated period of time, and/or the same are acknowledged by the corporate debtor.

(vi) Reliance placed by the applicant on the judgement of the Hon’ble Supreme Court for demonstrating that the provisions of the Limitation Act, 1963 are not applicable to the proceedings of Industrial Dispute Act, 1947 is highly irrelevant, in so far as the present proceedings are under the provisions of the Code and not under the Industrial Dispute Act, 1947.

(vii) Further, with regards to the RRC dated 03.02.2023 issued by Learned Labour Commissioner, it is submitted that the said RRC itself is invalid and in contravention of the provision of the Code, as the same is issued during subsistence of moratorium under section 14 of the Code.

(viii) Not only that, even the order dated 08.04.2021 of Hon’ble High Court of Madhya Pradesh, Gwalior in WP no. 8244/2021, which is time and again relied upon by the applicant, is passed during the subsistence of moratorium. Even otherwise, the said order dated 08.04.2021 passed by Hon’ble High Court categorically records this:

  • “Accordingly, this petition is disposed of by directing the respondent no. 2/Collector Bhind to implement the RRC within three months from the date of receipt of this order provided that there is no stay on orders of Labour Court/Industrial Court by higher Forum or there is no legal impediment. If there exists any legal impediment, the respondent no.2/Collector shall pass a detailed order and communicate the same to the petitioner. In absence of any such impediment, the RRC shall be executed within aforesaid time.”

Under the circumstances, the reliance placed by the applicant herein on the said judgment is highly misconceived and unwarranted.

(ix) The claim for gratuity amounts to the tune of Rs 2,88,191/-. The applicant has claimed the amount of gratuity for the first time in the present application. No such claim has ever been filed by the applicant before the respondent.

(x) The contention of the applicant that the workmen may be treated as secured financial creditor for an amount of Rs 12,07,750/- in light of judgment passed by the Supreme Court of India is highly non-genuine and unjustifiable. In the said case the person/bank in whose favour recovery certificate was issued was a financial creditor and the issue under determination before the Hon’ble Supreme Court was with respect to the period of limitation i.e. whether holder of recovery certificate would be entitled to initiate CIRP. Mere issuance of RRC shall not ipso facto make the workmen a financial creditor and that too a secured financial creditor. 

(xi) If it is to be presumed that the claim of the applicant of Rs 12,07,750/- as well as Rs 2,88,191/- totaling to Rs 14,95,941/- is to be admitted, then also considering the provisions of the resolution plan approved by the COC, they shall be entitled to an amount of 0.20% of their total claim. Thus, in such scenario, the workmen, in total, shall become entitled to receive a sum of Rs 2,992/- under the approved resolution plan.


# 4. In this context, rejoinder placed by the applicant and submission made therein are summarized here as under:

(i) Applicant never agreed with the decision of the respondent in rejecting the claim. Moreover, the applicant in para 18 of the application clearly stated that the applicant is claiming the claim amount only to the tune of Rs 12,07,750/- for RRC amount and Rs 2,88,191/- for Gratuity amount looking to the present situation, as the resolution plan is already been approved by the COC.

(ii) How the respondent came to know that the factory was closed in 2007 and no work was done, no electricity connection, no security, if he has all these records and information in possession then why he is not aware of the claim of the workers. How he ignored the claim of workman and the order of the Labour Tribunal and High Court. The attendance sheets are the records, responsibility of the corporate debtor and are in the possession of the corporate debtor qua the respondent and not the applicant.

(iii) The RRC issued by the Labour Commissioner is itself an execution proceeding under which the applicant has nothing to do whereas the government official will be going to take action on the basis of such RRC.

(iv) The RRC bearing No. 2/16/three/2023/4181-87 is not a fresh order passed during moratorium whereas the action against the corporate debtor has been taken well within year 2009 which can be ascertained from the show-cause notice dated 12.08.2009. As the applicant requested the labour department to give them a copy of RRC but the record of such RRC has been misplaced, therefore, a fresh RRC has been issued. There are no new proceedings initiated against the corporate debtor in the year 2023 and no fresh order has been passed.

(v) The moratorium is not applicable on the Writ jurisdiction of Hon’ble High Court under Article 226 of the Constitution of India. The Hon’ble NCLAT in the matter of Canara Bank versus Deccan Chronic Holdings Limited clearly held that the power of Hon’ble High Court under Article 226 of the Constitution of India cannot be curtailed by any other Act.


# 5. We have heard the learned counsel and learned PCS appearing for respective sides and have perused the relevant documents available on record. It is noted that the applicant being workmen of the corporate debtor had approached the Labour Commissioner for the unpaid salary. Learned Labour Commissioner on the basis of proceedings had issued two RRCs dated 22.06.2007 and 05.03.2008 in favour of the applicant amounting to Rs 26,05,548/- and Rs 54,42,943/- respectively. One more RRC was issued by the Learned Labour Commissioner dated 03.02.2023 amounting to Rs 30,33,819/- in favour of the applicant. The corporate debtor in the present case was admitted into CIRP by this Adjudicating Authority vide order dated 13.03.2020 and a resolution plan has already been approved by the CoC, which is pending for approval from this Adjudicating Authority. The applicant belatedly submitted their claims of Rs 83,12,822/- to the resolution professional of the corporate debtor, the same was rejected, vide email dated 09.09.2023 of the resolution professional on the ground that the claims made by the applicant pertain to the year 2007 and the same is barred by limitation. The applicant being aggrieved by the order of the resolution professional had preferred the present application before this Bench.


# 6. In defense, the resolution professional has taken several pleas which include that the claim of the applicant is barred by limitation; that the provision of the Industrial Disputes Act cannot be applied on the Limitation Act; that the applicant cannot be treated as financial creditors and more specifically as secured financial creditor; and that the applicant has not produced any proof to justify their claims from the year of 2007 as the factory was closed from February 2007.


# 7. After considering the above facts and circumstances, it is clear that the claims made by the applicant include the salary amount from the year 2007, gratuity amount, and amount as per the RRCs issued by the Learned Labour Commissioner. However, later the applicant restricted their claims to only the three RRCs amount of Rs 12,07,750/- and the gratuity amount of Rs 2,88,191/-. RP’s contention that the claim pertains to year 2007 and is barred by limitation is not acceptable, as the limitation act provides limitations for filing an appropriate application before a Tribunal or Court and does not specify a period to file a claim before the resolution professional in case of initiation of CIRP. Hence, in the present case the issue of rejection of the claim by the resolution professional on the basis that the claim made by the applicant are belated claims and barred by limitation can be overlooked and can be condoned, as the action for such claim was already taken by the applicant in time and the delay in execution of such RRC was on the part of the Government official appointed for execution of such RRC and the applicant cannot be held responsible for such delay on the part of execution. Further, it is the responsibility of an employer to make a provision with regards to the part of the gratuity amount payable towards the employees/workmen, so as to the part of the gratuity claim concerned that should be considered by the resolution professional.


# 8. Nevertheless, we note that the successful resolution applicant in the resolution plan approved by the CoC in the present case of the corporate debtor, has proposed an amount of Rs 50,000/- for the payment towards the operational creditor. Accordingly, the applicant will get a nominal amount with respect to their claim.


# 9. Be that as it may, we allow the claims of the applicant to the extent of RRCs issued by the Learned Labour Commissioner and the gratuity amount and set aside the order dated 09.09.2023 of the resolution professional rejecting the claims of the applicant. We direct the resolution professional to consider the claims of the applicant as it is not time-barred and take due steps to have a provision in the resolution plan in accordance with the provisions as contained in section 30(2)(b) and 30(4) of the Code.


# 10. Hence, we pass the following order:


ORDER

The application i.e. IA/308/MP/2023 in IA/280/MP/2022 in TP/152/MP/2019 [CP(IB)/99/2019] is partly allowed and stands disposed of.


----------------------------------------